Solar PowerRows of rooftop solar panels beside a wall-mounted inverter on a commercial building
On this page
  1. 01Before you start
  2. 02Fundamentals
  3. 03Where it sits in the project
  4. 04Architectures: on-grid, off-grid, hybrid
  5. 05Core components
  6. 06Sizing calculations
  7. 07Performance challenges
  8. 08Applications
  9. 09Installation and commissioning
  10. 10Check that it works
  11. 11Common problems and how to fix them
  12. 12Frequently asked questions
  13. 13Talk to PSS about solar

Solar on a site is not a catalogue product; it is an energy balance you have to close. Commercial buildings, factories, farms, telecom sites and remote infrastructure use PV to cut energy cost, improve resilience and support sustainability — but panels in the sun are not enough. Design needs loads, irradiance, losses, space, inverter limits, battery autonomy, protection and utility rules.

Pre-sales: accurate sizing avoids underperformance and wasted CAPEX. Site: mounting, strings, cable sizing, grounding, protection and commissioning decide safety and life.

Before you start

  • Monthly/hourly load and daytime share; existing board SLD and spare breaker capacity.
  • Roof/ground area, orientation, tilt, shading survey; structure loading and wind zone.
  • Architecture: on-grid / off-grid / hybrid; backup circuits, hours, chemistry, location.
  • Net-metering eligibility vs customer max load / caps; approvals (distribution company, EgyptERA, NREA as applicable).
  • Monitoring: plant-level or string-level with alarms; expansion and motor/AC surge loads.

Fundamentals

PV modules convert sunlight to DC. An inverter converts DC to AC for loads or an approved utility connection. Energy may be consumed on site, exported where permitted, stored in batteries, or run dedicated loads (e.g. irrigation pumps).

UnitMeaningExample
W / kWInstantaneous power500 W appliance; 10 kW inverter
Wh / kWhEnergy over time50 kWh/day facility use
kWpRated DC array capacity at STC20 × 550 W = 11 kWp

kWp ≠ daily kWh. Production depends on sun, temperature, shading, orientation, soiling, inverter losses and more. Size the array from energy demand and site resource; size inverter, cables, protection and batteries from their power, voltage, current and duty needs.

Where it sits in the project

Mechanically on roof or ground mounts; electrically on the LV main board via a dedicated PV breaker — or at MV via a step-up transformer on larger sites. Connected in parallel with the utility, not in series with the load — so utility protection settings and a bi-directional meter belong in scope.

Architectures: on-grid, off-grid, hybrid

On-grid (grid-tied)

Runs in parallel with the utility. Daytime PV serves loads; surplus may export if authorised; shortfall comes from the grid. Usually lowest CAPEX and no battery in a conventional layout. Limitation: a standard grid-following inverter shuts down on utility failure (anti-islanding, e.g. IEC 62116) so it must not be assumed to provide blackout backup. Backup needs island-capable equipment, isolation/transfer and usually batteries.

Off-grid

Independent of the utility — remote farms, buildings, telecom, monitoring sites. Typical: PV, inverter or DC power gear, batteries, charge controller or hybrid inverter with MPPT, protection and monitoring. Batteries cover night and low-sun periods. Challenges: autonomy, inverter surge/motor start, cloudy spells (generator or load management), temperature and lifecycle cost.

Hybrid

Grid + PV + batteries. Can prioritise self-consumption, charge storage, import, and back up selected loads when designed for islanded operation. Not every hybrid inverter can carry every load in an outage — backup kW, surge, SoC, PV availability and load selection decide.

AspectOn-gridOff-gridHybrid
UtilityYesNoUsually yes
BatteryUsually not requiredGenerally essentialUsually included
Without gridNormally no (IEC 62116)YesYes if designed for islanding
Best fitUrban / daytime loadRemote / no feederSavings + selected backup

Export, net metering and billing depend on regulation and utility approval — never assume they are automatic.

Egypt net-metering / self-consumption notes (verify current rules)

ItemPosition (as commonly applied)
Capacity vs customer loadMay not exceed the customer’s max load in the prior fiscal year (EgyptERA Decision 2/2020)
Caps20 MW/project; 25 MW aggregate/customer; 300 MW national under net metering (Decision 2/2020)
Merger fee / exemptionsFee bands by voltage (Circular 3/2022); exemptions and self-consumption rules updated in Circular 3/2023 — confirm before quoting
Battery in self-consumptionOften capped (e.g. ~20% of project capacity under Circular 3/2023) — verify current text

Licensing can set the real capacity ceiling before any engineering calculation.

Core components

Modules — mono-/polycrystalline silicon, thin-film where justified. Check Pmax, efficiency (modern crystalline often ~20%+ — use datasheet), Voc/Vmp/Isc/Imp, temperature coefficients, mechanical load, warranties, size/weight. High cell temperature cuts voltage and power vs STC.

Inverters — string, central, micro, hybrid, off-grid. Check AC kW, DC voltage/current/MPPT ranges and channel count, efficiency, environment, grid code. MPPT tracks the max-power point; use separate MPPTs for different orientations/shading — do not mix dissimilar strings on one tracker against OEM rules.

Batteries — LFP (LiFePO₄): high usable energy, deep cycle with BMS, higher CAPEX. Lead-acid (AGM/gel/flooded/OPzS): often lower CAPEX, more conservative DoD, more volume/weight, ventilation/maintenance as type requires. Preliminary DoD assumptions (~50% some lead-acid; ~80–90% some LFP) are not universal — datasheet rules. Size kWh (energy) and kW (power) separately.

Mounting — aluminium/galvanised steel for wind uplift, dead load, corrosion, waterproofing, access, tilt/row spacing. Egypt ~22–31° N: fixed arrays often face south near latitude tilt; east–west trades peak for a flatter daily curve. No single tilt is optimal everywhere.

BOS — DC/AC isolators and breakers, SPDs, string fuses where required, PV-rated DC cables/connectors, AC distribution, earthing/bonding, monitoring, labels, emergency shutdown. Select for real V/I/fault/environment — not every project needs the same combiner.

Typical standards in specs: modules IEC 61215/61730; inverter IEC 62109 / 61727; array wiring IEC 62548; lithium safety IEC 62619.

Sizing calculations

Use location-specific irradiance (peak sun hours as a planning aid — equivalent hours at 1,000 W/m²). Egypt specific yield often ~4.76–5.74 kWh/kWp/day (~1,700–2,100 kWh/kWp/year) before site losses — confirm with a site assessment/simulation.

Daily energy

Daily kWh = Power (W) × hours ÷ 1,000 (use realistic duty cycles). Prefer meter data.

Illustrative schedule → e.g. ~31.7 kWh/day (lighting, PCs, AC, pump, other). Proceed with a worked 50 kWh/day site:

Array capacity

kWp ≈ Daily kWh ÷ (PSH × PR) PR captures temperature, inverter, wiring, mismatch, soiling, etc. Do not double-count the same losses.

Example: 50 ÷ (5.5 × 0.80) ≈ 11.4 kWp. Egypt design often uses PR 0.75–0.80. A 100 kWp roof in Upper Egypt at PR 0.78 ≈ 148,000 kWh/year; unmanaged dust can cost ~5% more.

Energy-first thumb: monthly kWh × daytime share ÷ net specific yield. 20,000 kWh/month with 60% daylight → ~12,000 kWh from PV ≈ ~90 kWp at ~1,450 kWh/kWp net.

Module count and area

11,400 W ÷ 550 W ≈ 20.73 → 21 modules → 11.55 kWp. Count must also satisfy string V/I and layout.

Module ~2.2 × 1.1 m ≈ 2.42 m² → 21 × 2.42 ≈ 50.8 m² of module area — not total footprint. Add walkways, setbacks, fire access, row spacing, obstacles. Rough planning ~5–6 m²/kWp for some layouts only (≈57–68 m² for 11.4 kWp) — not universal.

Inverter and DC/AC ratio

DC/AC = array kWp ÷ inverter AC kW . Example 130 / 100 = 1.30. Ratios >1.0 are common; clipping occurs when DC available exceeds AC conversion limit — can be an intentional yield trade-off if OEM limits are respected. Egypt often uses 1.1–1.3. Also check simultaneous loads, motor start and backup kW — array kWp ≠ inverter AC capability.

Battery

Nominal kWh ≈ (Battery-supplied kWh/day × autonomy days) ÷ (usable DoD × battery-to-load efficiency) Example: (10 × 2) ÷ (0.80 × 0.90) ≈ 27.8 kWh. If PV covers daytime, the battery may not need full daily site demand. Off-grid thumb: 80 kWh/day × 2 days ÷ (0.8 × 0.9) ≈ 222 kWh — that number, not panel count, drives the argument.

String configuration

Series raises voltage; parallel raises current. Check cold Voc against inverter max DC (Voc rises as temperature falls). Example: 550 W module Voc 49.6 V → ~52 V at 5 °C (coeff. typically −0.25 to −0.35 %/°C); 18 modules ≈ 940 V — OK for 1,000 V inverter, not for 900 V. Hot Vmp must stay above MPPT min. Verify Imp/Isc per MPPT, string count, connectors, overcurrent protection. Never assume every inverter accepts 1,000 V or 1,500 V.

Performance challenges

Partial shading — trees, tanks, parapets, neighbours. Series mismatch hurts yield; separate MPPTs / optimizers / microinverters help but placement and string design come first.

Temperature derating — STC is 25 °C cell / 1,000 W/m²; real cells run hotter → less than nameplate W. Use power temperature coefficient and yield simulation; ventilate mounts where possible.

DC voltage drop — Vd = I × R_total ; R ≈ ρ L / A with both go and return. Calculate — do not prescribe 4/6/10 mm² by habit. Keep drop within project/standard limits (often aimed ~1–2% on DC). Use PV-rated cable and matched connectors.

Soiling — dust/sand/droppings; losses are site-specific — not a universal 15–30%. Clean from measured yield vs weather-adjusted expectation; follow OEM methods; never cold-wash hot modules or work live without procedure. Dusty sites need frequent inspection — “every 2–4 weeks” is not universal.

Clipping — AC output pinned at rating under strong sun; review logs and DC/AC economics.

Battery shortfall — undersized usable kWh, high simultaneous load, poor charging, temperature/BMS settings, surge demand. Re-check load profile, SoC history and continuous/surge ratings.

Applications

Residential — daytime offset ± selected backup. Commercial/industrial — daytime coincidence, demand, roof structure, export limits, harmonics/protection coordination. Agriculture / pumping — hydraulic duty: P_hyd = ρ g Q H ; electrical input ≈ hydraulic ÷ overall efficiency; water storage can beat batteries for irrigation. Telecom / remote — critical DC/AC, autonomy, seasonal yield, remote alarms, generator backup if needed. Critical hybrid backup — define which circuits, duration and shed list; backup port ≠ whole building; design transfer, neutral, earthing, fault protection.

Installation and commissioning

Before: loads, structure, shading, utility rules, BOM, drawings/string schedules, method statements.

During: approved mounts and torque, cable support, compatible connectors, DC/AC separation, earthing/SPD/isolation, labels, working-at-height and electrical safety.

Commission: polarity/strings, Voc checks, insulation (method safe for electronics), bonding, protection/isolators, inverter grid parameters, BMS/comms, monitoring/alarms, backup/transfer tests, as-builts. PV is live whenever illuminated — even with the inverter off.

Check that it works

  • String Voc/Imp match the design; cold Voc stays below inverter max DC.
  • Polarity, insulation, bonding, SPDs and isolators verified; inverter grid parameters set for the utility.
  • Monitoring and alarms report expected yield; backup/transfer tested where hybrid islanding is required.
  • As-builts, string schedules, datasheets and O&M handed over.

Common problems and how to fix them

String sized on nominal Voc

Trips on the first cold morning. Recalculate cold Voc and respect inverter max DC.

Shading ignored

Series mismatch kills yield. Redesign strings/MPPTs and placement.

DC cable without voltage-drop check

Calculate go-and-return drop; use PV-rated cable and matched connectors.

AC / household connectors on DC

Replace with PV-rated connectors and isolators.

No array DC isolator

Add isolation per design and code.

Soiling assumed at 2% with no cleaning budget

Measure yield vs weather-adjusted expectation; clean per OEM methods.

Battery sized on inverter rating not night load

Re-size usable kWh from autonomy and DoD.

Export assumed without available net-metering capacity

Confirm eligibility and caps before quoting.

Frequently asked questions

Does standard on-grid work in a blackout?

Normally no — anti-islanding. Need hybrid/backup design.

How many panels for 10 kW?

10,000 ÷ 550 ≈ 18.2 → ≥19 for >10 kWp (10.45 kWp) if layout/inverter allow. Distinguish 10 kWp array vs 10 kW AC inverter.

Space for ~10 kWp?

~19 × 2.42 m² ≈ 46 m² module area + setbacks/walkways.

kWp vs kWh?

Capacity at STC vs energy over time.

What is clipping?

DC available > inverter AC limit — may be intentional within OEM rules.

Is LFP always better than lead-acid?

Not always — compare usable energy, cycle life, temperature, CAPEX, maintenance, warranty.

Cleaning interval?

Site-driven from soiling and recovered energy — not universal.

Can PV run AC / motors?

Yes if array, inverter and battery sized for continuous and start/surge.

Is a battery always required?

No for conventional on-grid; yes typically for off-grid; hybrid when storage/backup needed.

What inputs does a quotation need?

Location, architecture, utility rules, daily/peak demand, motors, backup duration, area, shading, schedule, expansion — plus datasheets and drawings for final design.